Every client has a different plan for their property, whether that be an outdoor kitchen, patio, kitchen remodel, bathroom remodel or whole home remodel just to name a few. Below are just a couple examples of our processes for bathroom and kitchen renovation or remodels.
Bathroom and Kitchen Renovation Schedule (Cosmetic Remodel)
For cosmetic-only renovations, we will give an estimate to clients. For more extensive remodeling projects, we will need to see the design created from client to designer and have the selection budget for us to give an accurate estimate.
- Go over the scope of work
- Give ideas and suggestions
- Discuss Clients’ expectations
- Go over the living situation while under construction
- Discuss time frames
- Discuss access to the house and staging area.
- For cosmetic-only renovations, we will give an estimate to clients. For more extensive remodeling projects, we will need to see the design created from the client to the designer and have the selection budget for us to give an accurate estimate.
Phase 1: Pre-Construction (1–2 Days)
- Finalize design selections (tile, fixtures, finishes)
- Confirm material orders & delivery dates
- The scheduled project start date
- Set up dust protection and an access plan
Phase 2: Demolition (1–2 Days)
- Remove existing cabinets, countertops, fixtures, tile, or flooring
- Haul away debris
- Inspect framing, subfloor, HVAC, plumbing, and electrical; review any issues with client
Phase 3: Rough-In Work (5–7 Days)
- Plumbing for new fixtures
- Electrical for lighting, outlets, fans, etc.
- Framing (niche, bench, shelving, etc.)
Phase 4: Inspections (1 Day)
- Plumbing & electrical rough-in inspections
- Framing inspection
- Location verification of fixtures, niches, shelves, and benches (signed off by client)
Phase 5: Walls & Floors (2–4 Days)
- Install cement board / drywall and waterproofing as needed
- Tile installation (floor, shower walls, backsplash)
- Grouting
Phase 6: Paint & Finishes (1 Day)
- Paint walls
- Paint ceiling
- Touchup trim
Phase 7: Fixture Installation (2–5 Days)
- Install vanity, cabinets, countertops, sinks, faucets, shower glass, backsplash
- Install lighting and exhaust fans
Phase 8: Final Inspection & Walkthrough (1 Day)
- Final punch list
- Client walkthrough and sign-off
- Final clean-up
SPECIAL NOTES
- Schedule may shift due to inspections, unforeseen repairs, code issues, or material delays.
- We provide regular updates and notify you of any changes.
Remodel Schedule
Focused on single-room upgrades like kitchens or baths: planning, selections, demo, install, clean-up, and handover.
For cosmetic-only renovations, we will give an estimate to clients. For more extensive remodeling projects, we will need to see the design created from client to designer and have the selection budget for us to give an accurate estimate.
- Go over the scope of work
- Give ideas and suggestions
- Discuss Clients’ expectations
- Go over the living situation while under construction
- Discuss time frames
- Discuss access to the house and staging area.
- For cosmetic-only renovations, we will give an estimate to clients. For more extensive remodeling projects, we will need to see the design created from the client to the designer and have the selection budget for us to give an accurate estimate.
Phase 1: Pre-Construction (1–2 Days)
- Finalize design selections (tile, fixtures, finishes)
- Finalize floor plans and framing plans if needed
- Confirm material orders and delivery dates
- The scheduled project start date
- Set up dust protection and an access plan
Phase 2: Demolition (2–4 Days)
- Remove existing walls and sheetrock
- Remove plumbing, electrical, and HVAC vents/returns as needed
- Remove fixtures, tile, flooring, vanity, cabinetry, etc.
- Haul away debris
- Inspect framing, subfloor, HVAC, plumbing, and electrical. Review the findings with clients.
Licensed, Insured, & Warranty-Backed
- Relocate plumbing drains and backfill with concrete if needed
- Plumbing rough-in for new layout
- Electrical rough-in for lights, outlets, fans, etc.
- Framing adjustments (new walls, ceiling modifications, structural changes)
Phase 4: Inspections (1 Day)
- Plumbing & electrical inspections
- Framing inspection
- Location check and client sign-off
Phase 5: Insulation, Sheetrock & Paint (5–7 Days)
- Install insulation where required
- Hang sheetrock, tape, float, and texture
- Install trim (interior doors, casings, window stools and skirts, etc.)
- First coat of paint on walls and trim
Phase 6: Walls & Floors (2–4 Days)
- Install cement board/drywall, waterproof shower areas
- Tile installation (floors, walls, backsplash)
- Adjust the process if the flooring is wood, laminate, or LVP
Phase 7: Paint & Finishes (1 Day)
- Final coat of paint on walls and ceiling
- Touch-up trim as needed
Phase 8: Fixture Installation (2–5 Days)
- Install vanities, cabinets, countertops, sinks, faucets, and accessories
- Install kitchen backsplash
- Install shower glass, lighting, and exhaust fan
Phase 9: Final Inspection & Walkthrough (1 Day)
- Complete punch list items
- Client walkthrough and sign-off
- Final clean-up
Special Notes
- Timelines may shift due to inspections, unforeseen repairs, code compliance, or material delays.
- We provide weekly updates and notify you of changes.
- For whole-home remodels, schedules are custom-tailored to fit client needs and living arrangements.
HBH Renovations proudly serves homeowners throughout the Texas Hill Country, including Canyon Lake, New Braunfels, Spring Branch, Blanco, Wimberley, Seguin, Fischer, Johnson City, Boerne, San Marcos, and surrounding communities. Whether you’re ##upgrading a kitchen, remodeling a bathroom,## or adding valuable square footage, our skilled team delivers quality craftsmanship and a seamless process from the first design concept to the final walk-through.